• South Thach Han Reservoir

    South Thach Han Reservoir

      19/03/2014
    Project location: Thach Han river in Quang Tri
    Construction time: Commencement: 3/1978 - Completion: 2002.
    Project managers: Le Van Khuong, Pham Khac Minh Hung, Pham Vu Liem
    Project tasks: Irrigating 17,000 ha of cultivated land 
  • Lower Ayun Reservoir

    Lower Ayun Reservoir

      18/03/2014
    Project location: Headworks group is located on Ayun river in Ho Bong commune, Chu Se district, Gia Lai province (2000).
    Consultancy contents:
    - Geological investigation
    - Topographic survey
    - Preparation of feasibility study report
    - Preparation of technical design + Total cost estimation
    - Preparation of detailed design + Cost estimation
    Project Managers: Tran Dang Am, Le Dinh Tuyet 
  • Upper Easoup Reservoir

    Upper Easoup Reservoir

      14/03/2014
    Project location: On upstream of Easuop stream in Chu Ma Lanh commune, Easup district, Dak Lak province.
    Construction time: Commencement on 12/6/2001
    Project managers: Hoang Minh Dzung, Phan Nhu Hai, Nguyen Huu Ngoc
    Project tasks:
    - Irrigation area: 9455 ha
    - Supplying water for domestic use
    - Aquaculture
    - Improving climate
    - Generating power, N=1600 kw 
  • Tan Giang Reservoir Project

    Tan Giang Reservoir Project

      13/03/2014
    Project location: Lu river, Ninh Thuan province
    Construction time: 1998, 2001
    Project managers: Gia Kim Hung,Tran Minh Tan
    Project tasks:
    Irrigating 3000 ha of cultivated land of Ninh Phuoc district.
    Supplying water for domestic use
    Retarding flood 
  • Long Song Reservoir

    Long Song Reservoir

      11/03/2014
    Project location: Long Song river, Binh Thuan province
    Construction time: Commencement in 2001
    Project managers: Le Van Ngo - Do Van Xung - Phan Van Luong
    Project tasks: Irrigating 4260 ha 
  • Ta Trach Reservoir

    Ta Trach Reservoir

      08/02/2014
    Project location: Ta Trach river in Duong Hoa commune, Huong Thuy district, Thua Thien Hue province
    Construction time: Investigation and design time: 2000-2005
    Construction commencement: 26-11-2005
    Project managers: Luong Van Nguyen, Phan Vinh Khanh
    Project tasks:
    + Controlling early flood, mitigating major flood for Huong river system.
    + Supplying water for domestic and industrial uses with Q = 2.0 m3/s
    + Creating stable irrigation source for 34,782 ha of cultivated land in Huong river delta area.
    + Adding fresh water source for downstream of Huong river to push saline intrusion, improve environment in lagoon area, aquaculture with Q = 25.0 m3/s.
    + Generating power with installed capacity N=19.5 MW 
  • Cua Dat Reservoir

    Cua Dat Reservoir

      21/01/2014
    Project location: Chu river - Thuong Xuan district, Thanh Hoaprovince
    Construction time: Investigation and design time: 1999-2004
    Commencement time: 02/02/2004
    Project managers: Dinh Xuan Tu, Le Van Ngo, Le Manh Hiep, Hoang Minh Dzung, Vo Van Lung
    Major technical parameters: - Work grade: I; - Catchment area: 5938 km2; - Normal water level (NWL): 110 m; - Dead water level (DWL): 73 m; - Total storage capacity: 1,450 million m3; - Effective storage capacity: 793.70million m3; - Dead storage capacity: 268.69million m3