Bac Hung Hai Sluice
17/02/2014Project location:
- Red river
- Xuan Quan headworks group
Project tasks: - Natural land area in the project area: 185 000 ha; - Supplying irrigation water to 110,000 ha, draining 94,000 ha in Bac Ninh province
Project managers: Nguyen Hoang, Nguyen Van Thuy, Nguyen Xuan Thi, Tran Ngoc Lai, Pham Khac Minh Hung, Nguyen Xuan LamVan Coc Intake
17/02/2014Project location: Phuc Tho district, Hanoi
Construction time: 2002-2004
Project managers: Phan Vinh Khanh; Nguyen Manh Cuong
Project tasks:
- Together with Ben Mam, Lien Mac, Tac Giang intakes to get water from Red river to supply to Day river for restoring flow in Day river in dry season when necessary.
- Obtaining silt water in flood season, supplying water to downstream area for production and domestic uses.
- Improving cultivation land, ecological environment, water navigation.
- Not affecting flood diversion from Red river to Day river.Nhue River Sluice
13/02/2014Project location: Nhue river in Hanoi, Ha Tay and Ha Nam
Construction time: 1932-1940: the French; 1960-2002: HEC-1
Project managers: Ngo Quoc Trung; Nguyen Xuan Duong
Project tasks: Irrigating 60,000 ha; Draining 107,500 ha; Water navigation
Latest news
Environmental impact assessment
23/10/2013Development of HEC over periods
23/10/2013Construction design consultancy of works
23/10/2013