Tan Chi Pumping StationProject location: Duong River in Bac Ninh province Construction time: 2001 Project managers:Le Van Ngo - Phung Van Luyen - Phan Vinh Khanh Project tasks: Draining an area of 6420 ha surrounded by Con Tieu stream, South Trinh Xa canal, Hanoi-Lang Son railway and Duong riverdike. Major technical parameters: Drainage area : 5 km2 Workgrade : III Rainfall frequency : p=10% Drainage regime: 5-day rainfall 7-day drainage Drainage coefficient : q=4.85 l/s/ha Discharge Q = 31.10 m3/s Design water level at suction sump during draining : +2.00m Minimum water level at suction sump during draining : +1.70m Maximum water level at suction sump during draining: +3.29m Minimum water level at discharge basin : +5.80 m Topographic head = 8.20 m Design head = 9.00 m Scale and structure of main works: Headworks: Repairing existing pumping station: replacing 46 old pumps with 22 horizontal axis pumps type 12-LTX800-9, replacing 46 out-of-order pumps with 900z/h horizontal axis pumps type HL900-9. New pumping station: Q=16m3/swith 4 imported pumps +Station house: open type, length of the house: 26.45; 4 pump rooms, 01 assembly room, 01 electric room. + Suction room: elevation: (-2.25) + Pump and assembly rooms: floor elevation (+4.50) + Electric room: + Suction sump and inlet of suction room: basin length: 62m, width: 50m. + Discharge basin: a separated one, basin length: 4.50m, width: 17.65m. + Area of the station: (10m x 16m) + Dyke crossing culvert: dimension: 2.5 x 2.5m. Bottom elevation (+5.20). + Canal system connecting to the suction sump Total hits 67 - Last update 20/03/2014 03:11' CH |
|