Tuyen Quang Hydropower Project1. Location: Na Hang district, Tuyen Quang province 2. Stage: Technical design stage 1 and 2 - Tasks: + Flood control with storage capacity of 1 billion m3; + Power generation: installed capacity of 342MW, annual average power output: 1,295x106 KWh. + CFRD. Maximum dam height: 124.5m; dam length: 99.5m; + Spillway: 4 gates (15 x 15.15 ) m ; 8 bottom outlets (4.5 x 6); Q = 0.02%: 12,736 m3/s This is the second largest hydropower project in the North with total investment cost of CND 7,500 billion. The FS of the project was approved by the Government on 19/04/2002, the project was commenced on 22/12/2002. Parameters of the project: - Maximum dam height: 92.2 m; - Dam crest width: 10 m - Reservoir storage capacity: 2,245 billion m3; - Number of unit: 3; - Design capacity: 342 MW - Construction time: 5 years; - Excavation and filling quantity: 13 million m3 rock and soil; - Concrete placement: 950x 103 m3 - Equipment installation: ~ 15 x 103 ton Total hits 91 - Last update 28/02/2014 04:43' CH |
|